Thursday, May 16
This week, May 13 through May 17, expect lane, ramp and street closures along US-50 in Sacramento.
Nearby residents can expect loud construction noise as contractors are scheduled to perform demolition work, remove concrete, and conduct striping activities.
*All work is scheduled to begin as listed but subject to change due to traffic incidents, weather, availability of equipment and/or materials, and construction related issues.
Nighttime Work
Thursday, May 16 (9PM-5AM)
- Eastbound auxiliary lanes from I-5 to 16th Street
- Riverside Blvd. onramp
- 15th Street offramp
- Eastbound #1 and #2 lanes from 59th St. to Howe Ave.
- Westbound #3 and #4 lanes from 65th St. to Stockton Blvd.
- Westbound 65th St. onramp
- Westbound 59th St. onramp
- Westbound Stockton Blvd. offramp
- Westbound Howe Ave. onramp + auxiliary lane
- Westbound #1 and #2 lanes from Stockton Blvd. to 34th St.
- Stockton Blvd. under the US-50 project area
- Eastbound #1 and #2 lanes from 59th St. to Howe Ave.
- Eastbound #4 lane from Howe Ave. to Watt Ave.
- Eastbound Howe Ave. onramp
- Eastbound Watt Ave. offramp
Friday, May 17 (9PM-5AM)
- Eastbound auxiliary lanes from I-5 to 16th Street
- Riverside Blvd. onramp
- 15th Street offramp
- Eastbound #1 and #2 lanes from 59th St. to Howe Ave.
- Westbound Howe Ave. onramp + auxiliary lane
- Westbound #1 and #2 lanes from Stockton Blvd. to 34th St.
Saturday, May 18 (9PM-5AM)
- Westbound #1 and #2 lanes from Stockton Blvd. to 34th St.
Sunday, May 19 (9PM-5AM)
- Westbound Stockton Blvd. offramp
- Westbound auxiliary lane from 59th St. onramp – Stockton Blvd. offramp
- Westbound 59th St. onramp
- Westbound #1 and #2 lanes from Watt Ave. to Howe Ave.
- Westbound Howe Ave. onramp
- Westbound #1 and #2 lanes from Stockton Blvd. to 34th St.
- Stockton Blvd. under the US-50 project area