Fix 50 Project Status

  • 85%

Projected Completion Date

Summer 2025

Announcements

Thursday, May 16

This week, May 13 through May 17, expect lane, ramp and street closures along US-50 in Sacramento.

Nearby residents can expect loud construction noise as contractors are scheduled to perform demolition work, remove concrete, and conduct striping activities.

*All work is scheduled to begin as listed but subject to change due to traffic incidents, weather, availability of equipment and/or materials, and construction related issues.

Nighttime Work

Thursday, May 16 (9PM-5AM)

  • Eastbound auxiliary lanes from I-5 to 16th Street
  • Riverside Blvd. onramp
  • 15th Street offramp
  • Eastbound #1 and #2 lanes from 59th St. to Howe Ave.
  • Westbound #3 and #4 lanes from 65th St. to Stockton Blvd.
  • Westbound 65th St. onramp
  • Westbound 59th St. onramp
  • Westbound Stockton Blvd. offramp
  • Westbound Howe Ave. onramp + auxiliary lane
  • Westbound #1 and #2 lanes from Stockton Blvd. to 34th St.
  • Stockton Blvd. under the US-50 project area
  • Eastbound #1 and #2 lanes from 59th St. to Howe Ave.
  • Eastbound #4 lane from Howe Ave. to Watt Ave.
  • Eastbound Howe Ave. onramp
  • Eastbound Watt Ave. offramp

Friday, May 17 (9PM-5AM)

  • Eastbound auxiliary lanes from I-5 to 16th Street
  • Riverside Blvd. onramp
  • 15th Street offramp
  • Eastbound #1 and #2 lanes from 59th St. to Howe Ave.
  • Westbound Howe Ave. onramp + auxiliary lane
  • Westbound #1 and #2 lanes from Stockton Blvd. to 34th St.

Saturday, May 18 (9PM-5AM)

  • Westbound #1 and #2 lanes from Stockton Blvd. to 34th St.

Sunday, May 19 (9PM-5AM)

  • Westbound Stockton Blvd. offramp
  • Westbound auxiliary lane from 59th St. onramp – Stockton Blvd. offramp
  • Westbound 59th St. onramp
  • Westbound #1 and #2 lanes from Watt Ave. to Howe Ave.
  • Westbound Howe Ave. onramp
  • Westbound #1 and #2 lanes from Stockton Blvd. to 34th St.
  • Stockton Blvd. under the US-50 project area

Reminders and Resources

Crews are working around the clock so always Be Work Zone Alert. The speed limit in the work zone is 55 MPH and CHP will be patrolling the area to issue citations to motorists that exceed that limit.

General work schedule (subject to change): Day work from 5 AM – 8 PM; night work from 8 PM – 5 AM.

To submit complaints about noises or work, please fill out the ‘Contact Us’ form below or contact Caltrans Public Information Officer Dennis Keaton at dennis.keaton@dot.ca.gov.

Access more information on planned highway maintenance and construction work in District 3 here: https://lcswebreports.dot.ca.gov/searchdistricts?district=3 

For real-time highway conditions visit: https://quickmap.dot.ca.gov/ #KnowBeforeYouGo

Ongoing Project Work and Closures

  • Crews continue to work within the construction area from I-5  to Watt Avenue.
  • 35th Street is closed near the Stockton Boulevard off-ramp at US-50 and scheduled to reopen 2024.
  • Loud noises can be expected.

Thank you for your patience as we’re #RebuildingCa for years to come.

Contact Us

    Project Map

    Connect for the Latest Roadwork News


    2 days ago

    Fix 50
    The latest #Fix50 updates are just a text away!Text ‘Fix50’ to 41372 to start receiving closure notifications. See MoreSee Less
    View on Facebook

    5 days ago

    Fix 50
    Happy #MothersDay! Let's work together to make sure all moms, their families, and everybody on the roadway stays safe in the project area today and every day.Remember to drive safely through the #Fix50 work zone. #BeWorkZoneAlert See MoreSee Less
    View on Facebook

    Be Work Zone Alert
    FHWA
    SACOG
    Caltrans
    SB1
    Measure A
    Sacramento Transportation Authority
    Protect Every Drop
    Caltrans' Winter Driving Tips
    California All COVID-19 Updates
    CHP
    Flatiron

     

    Caltrans' Quick Map