Legislation to speed up Owatonna to Dodge Center construction takes first step in Senate
After the Legislature passed $160 million in trunk highway bonds to complete the Owatonna to Dodge Center project in May of last year, Minnesota Management and Budget (MMB) identified an issue with the bonding language that could delay construction by up to three years.
While it was the legislature’s intent to give MnDOT the flexibility to construct Corridors of Commerce projects like Highway 14 when each project was ready to go, the language of the bill complicated matters.
Although MnDOT staff is ready to start preparation work on Highway 14 right away, the MMB and MnDOT determined that unless the Legislature adopted clarifying legislation, the bonds to fund the project could not be sold by the state until 2022.