What's New with PDX Next: Airport Way, Ticket Lobby and Baggage Claim Updates
Airport Way: Beginning Monday, Oct. 16, through Friday, Oct. 20, expect lane changes eastbound on Airport Way. Through lanes will be narrowed during daytime hours for construction work on the TriMet Better Red project.
Ticket Lobby: During daytime work hours on Friday, Oct. 13, through Friday, Oct. 27, crews will perform demolition work over and adjacent to the former common use ticket counters in the central ticket lobby. Impacts may include noise, vibrations and odor – monitoring of these impacts will be in place. Work zone access and material haul will take place behind the wall in the construction area and won’t impact the ticket lobby.
Baggage Claim: While work continues along main bag road, baggage carousel 10 will close from 6:30 a.m. to 4 p.m. on Wednesday, Oct. 11, and Thursday, Oct. 12. United will use baggage carousel 9 during the shutdown.
Crane Pick: For safety while cranes are moving materials, the B/C bypass will close for about 90 minutes on Tuesday, Oct. 17 from 1:30 to 3 a.m. Employees with red badges will have alternate route access through the security doors, but grey badge employees will not. Spotters will be in place throughout the bypass to prevent entry.
Coming Soon: In exciting news, we're getting close to completing a series of ground transportation projects that will make it easier to get in and out of PDX faster. Rideshares and taxis will soon have a new home on the first floor of the short-term parking garage, and an updated PDX station on MAX Red Line opens this Sunday, Oct. 22. More details coming next week!
Looking for more PDX Next information? We're keeping you in the know on what's new on the PDX People website. Have questions or suggestions about construction? Email hello@pdxnext.com or call the construction hotline at 503.460.4339.