Progress Being Made; Businesses Stay Positive
Upcoming this week:
-Foundation for the seat blocks and planter beds will continue to be placed
-Subdrain will be installed along the curb line
-The road subgrade will be prepped, and the subbase and base will be hauled in and placed in preparation for concrete paving. 300 Block concreate paving is anticipated to begin in approximately two weeks