Activity #1: Elevator Access Route Changes
施工項目一:停車場電梯出入通道調整
|
|
|
|
| Pedestrian access to the garage elevators will remain open at all times. |
Crews continue demolition and waterproofing work in front of the elevators, and a new walkway to the Washington Street sidewalk has been built.
One or two elevators may close intermittently, but at least one will remain in service at all times while the garage is open.
|
施工人員繼續在電梯前方進行拆卸及防水工程,並已增設一條連接華盛頓街人行道的臨時出入斜道。
施工期間,一至兩部電梯可能會間歇性暫停服務,但在停車場開放時間內,將確保至少一部電梯全程維持正常運作。
|
|
|
|
Pedestrian pathway from Washington Street to the elevator.
由華盛頓街通往電梯的行人通道。
|
|
| Pedestrian pathway from Washington Street to the elevator.
由華盛頓街通往電梯的行人通道。
|
|
|
|
Pedestrian pathway from the elevator to Washington Street.
由電梯通往華盛頓街的行人通道。
|
|
| Pedestrian pathway from the elevator to Washington Street.
由電梯通往華盛頓街的行人通道。
|
|
|
|
Activity #2: Park Expansion Toward Kearny Street | Sept. 28 - Dec. 1
施工項目二:公園向乾尼街方向擴建|9月28日至12月1日
|
To create more park space, the park will extend about 8 feet toward Kearny Street above the garage entrance. Crews will build a new support structure around the existing garage entrance and exit.
Temporary lane closures may be needed during demolition and construction, but garage access will remain open. Flaggers will help manage traffic in and out of the garage.
|
為增加公園空間,位於停車場入口上方的公園範圍將向乾尼街方向延伸約8呎。施工人員將在現有停車場出入口周邊興建新的支撐結構。
拆卸及施工期間,部分行車線可能需要臨時封閉,但停車場出入口會維持開放。現場將安排交通指揮人員,協助車輛安全進出停車場。
|
Activity #3: Temporary Garage Shoring and Parking Impacts | Oct. 6 - Jan. 24
施工項目三:停車場臨時承托結構及停車影響|10月6日至1月24日
|
Temporary shoring will be installed on Floors 2, 3 and 4 of the garage to support grade beam and trellis work in the park. The shoring is expected to remain through Jan. 24, 2027.
During this period, 80 parking spaces will be temporarily unavailable - 40 each on Floors 3 and 4. Both garage entry lanes will remain open, while the middle exit lane will be temporarily closed.
|
為配合公園內的地樑及棚架工程,停車場第2、3及4層將安裝臨時承托結構。相關結構預計將保留至2027年1月24日。
期間將有80個停車位暫時停用,其中第3層及第4層各40個。停車場兩條入口行車線將維持開放,中間一條出口行車線則會暫時關閉。
|
Activity #4: Sewer Maintenance and Replacement on Walter U. Lum Place | Oct. 8 - Nov. 10
施工項目四:林華耀街 (Walter U. Lum Place) 污水管道維修及更換工程|10月8日至11月10日
|
Sewer line maintenance and replacement work will take place on Walter U. Lum Place. Crews will perform trenching in the roadway to access and replace the sewer line.
|
-
Daytime trenching will take place from 7 a.m. to 3 p.m. Walter U. Lum Place will be closed to vehicles during work hours and reopened afterward.
- Sewer replacement will be completed over two nights, requiring a full closure of Walter U. Lum Place during the nighttime work.
|
Temporary road closures, traffic changes, construction noises and parking restrictions are expected near the work area. The project team aims to minimize disruptions. The west-side sidewalk will remain open and local businesses will remain accessible to pedestrians.
|
林華耀街將進行污水管道維修及更換工程。施工人員將在路面開挖溝槽,以進入地下並更換污水管道。
|
- 日間開挖工程: 每日上午7時至下午3時進行。施工期間,林華耀街將暫停車輛通行,工程時段結束後重新開放。
-
夜間污水管更換工程: 工程將分兩晚進行,期間需要全面封閉林華耀街。
|
工程範圍附近將實施臨時封路及交通繞行,並或有施工噪音及停車限制。西側人行道將維持開放,沿線商戶照常營業。
|
Monthly Office Hours
每月社區諮詢時段
|
Second Friday of each month at 10:00 a.m. at Walter U. Lum Place and Washington Street.
For language services or accessibility requests, please contact Noah Levy, project manager, at noah.levy@sfgov.org at least 48 hours before the meeting. Late requests will be honored if possible.
|
每月第二個星期五上午 10 時,在林華耀街 (Walter U. Lum Place) 與華盛頓 (Washington) 街交界處。
如需其他語言或無障礙支援,請於會議前至少 48 小時電郵項目經理Noah Levy: noah.levy@sfgov.org。逾時將盡力安排。
|
|
|
|
Scaffolding and protective wraps are being installed around the Chinatown Public Health Center building.
華埠公共衞生局大樓周邊正在搭建棚架及安裝防護膜。
| |
|
|
Upcoming construction activities and traffic impacts: |
Phase A partial tunnel closure remains in effect
|
- Expect traffic delays during peak travel times. Drivers who want to avoid delays should consider using the local and regional detour routes established for the full closure.
|
Activities in October 2026 |
-
Hazardous materials abatement inside the closed tunnel bore is expected to be completed by Oct. 2, pending environmental clearance.
- Hazardous materials abatement inside the building will continue through October.
- Preparation for structural demolition inside the closed tunnel bore will begin in early October.
-
Structural demolition of the building is expected to begin in late October or early November.
- Scaffolding and protective wraps are being installed along the Broadway tributaries and other work areas to support demolition and abatement.
- Public Works will continue on-site traffic control and utility coordination near the tunnel.
|
- 高峰時段或有交通延誤。駕駛人士如欲避免延誤,請改用附近及區域繞行路線。
|
- 已封閉隧道内的有害物質處置工程預計於10月2日完成,惟最終須待通過環境檢測合格。
- 大樓內部的有害物質處置工程將持續至10月底。
- 已封閉隧道內的結構拆卸準備工作將於10月初展開。
- 大樓內部的結構拆卸工程預計於10月底或11月初展開。
- 百老匯沿線支路及其他施工範圍正搭建棚架及安裝防護膜,以配合拆卸及有害物質處置工程。
- 工務局將繼續於隧道附近進行現場交通管制及公用設施協調工作。
|
|
|
|
The Chinatown Branch Library Renovation Project is expected to begin construction in December 2026. Additional updates will be shared as the project moves into the construction phase.
|
華埠麥禮謙圖書分館改善工程預計於 2026 年12月動工。隨著項目進入施工階段,市府將陸續提供更多最新動態。
|
|
|
|
Chinatown Transportation Updates
華埠交通最新消息 |
|
|
|
The City will monitor transportation conditions during construction activities. Traffic and transit reroutes are subject to change. Check SFMTA.com/gochinatown for the latest information before traveling. If the link does not open, please copy and paste it into your browser.
市府將於施工期間密切留意交通狀況。道路交通及公共運輸繞行安排或會因應實際情況作出調整。出發前,請瀏覽 SFMTA.com/gochinatown 獲取最新資訊。如未能打開,請將網址複製並貼到瀏覽器開啟。
|
|
|
|
Chinatown Public Restroom Map
華埠公廁指南
|
|
|
|
| 1. Willie “Woo Woo” Wong Playground 黃顯護遊樂場
830 Sacramento Street, San Francisco, CA 94108
Spring/Summer: 8 a.m. - 8 p.m. | 春季及夏季:上午八時至晚上八時
Fall/Winter: 8 a.m. - 5:30 p.m. | 秋季及冬季:上午八時至下午五時半
|
2. Chinatown - Rose Pak Station Upper Plaza (Opening Sept. 19) |
華埠白蘭地鐵站上層廣場 (9月19日起開放)
943 Stockton Street, San Francisco, CA 94108
Monday - Saturday, 8 a.m. - 8 p.m. | 星期一至六:上午八時至晚上八時
|
3. St. Mary's Square | 聖瑪麗公園
651 California Street, San Francisco, CA 94108
Spring/Summer: 8 a.m. - 8 p.m. | 春季及夏季:上午八時至晚上八時
Fall/Winter: 8 a.m. - 5:30 p.m. | 秋季及冬季:上午八時至下午五時半
|
4. Betty Ann Ong Recreation Center | 鄧月薇華人康樂中心
1199 Mason Street, San Francisco, CA 94108
Tuesday - Friday: 10 a.m. - 9 p.m. | 星期二至五:上午十時至晚上九時
Saturday: 9 a.m. - 5 p.m. | 星期六:上午九時至下午五時
|
|
|
|
SHOP & DINE LOCAL IN CHINATOWN!
施工期間 請支持華埠本地商家 |
|
|
|
San Francisco Public Works is committed to supporting our neighborhood merchants during construction. Please continue to shop, dine and support local Chinatown small businesses while project improvements are underway!
Plan your visit with the Perfect Day in Chinatown guide: https://www.sf.gov/perfect-day-chinatown
Explore more local businesses through Office of Economic & Workforce Development's Shop and Dine SF page: https://www.sf.gov/shop-dine-sf
|
|
|
|
Get project updates and community information
獲取項目最新消息及社區資訊 |
|
|
|
|
For project updates, please contact San Francisco Public Works Public Affairs at chinatownprojects@sfdpw.org or (415) 269-9199.
To receive construction updates in Chinese, please join our WeChat group to receive the latest project information. To join, please scan the WeChat QR code or contact us for assistance.
|
|
|
|
Manage your preferences | Opt Out using TrueRemove™
Got this as a forward? Sign up to receive our future emails.
View this email online.
|
49 South Van Ness Avenue | San Francisco, CA 94103 US
|
|
|
|
This email was sent to .
To continue receiving our emails, add us to your address book.
|
|
|
|
|