Chinatown Improvement Projects
Construction Updates
華埠改善工程最新消息 |
|
|
|
-
Beginning September 19: Chinatown - Rose Pak Station upper plaza restrooms will be open to the public Monday through Saturday, 8 a.m. to 8 p.m., during Portsmouth Square construction.
- October: Crews are expected to begin sewer maintenance and replacement on Walter U. Lum Place. Work will require roadway trenching and a temporary street closure. Schedule details will be shared once confirmed.
|
-
九月十九日起:花園角施工期間,白蘭地鐵站上層廣場公廁將於星期一上午八時至晚上八時開放。
- 十月:工程隊預計於林華耀街 (Walter U. Lum Place) 展開污水管道維修及更換工程。工程涉及路面開挖及臨時封路。具體施工安排將於確認後公佈。
|
|
|
|
Public Art Proposals | Shared by the San Francisco Arts Commission
公共藝術提案 | 資料由三藩市藝術委員會提供
|
|
|
|
Artist 藝術家: Twin Walls Mural Company
Location 位置: exterior wall 外墻
|
|
|
Artist 藝術家: Vida Kuang 鄺楚瑩
Location 位置: interior wall 內牆
|
|
|
|
Artist 藝術家: Mik Gaspay
Location 位置: interior wall 內牆
|
|
|
Artist 藝術家: Monyee Chau
Location 位置: interior wall 內牆
|
|
|
|
Upcoming construction activities and traffic impacts: |
Phase A partial tunnel closure remains in effect
|
-
Expect traffic delays during peak travel times. Drivers who want to avoid delays should consider using the local and regional detour routes established for the full closure.
|
Activities in September 2026 |
- Hazardous materials abatement continues inside the closed tunnel bore and building interior.
- Sept. 3: site logistics zone begins on Mason Street. Fencing will be installed along the Mason Street sidewalk, with a temporary pedestrian path maintained at all times.
- Sept. 4 to 5: PG&E gas shutoff work and roadway restoration are scheduled. Temporary parking restrictions are expected along the Broadway north tributary road.
-
Starting Sept. 8: site logistics zones begin on the Broadway tributary roads to support rooftop and façade demolition. Scaffolding and shrink wrap will be installed around the building. The parking lane will be converted to a traffic lane, with temporary parking restrictions expected.
- Sept. 11 to 14: Dragon artwork removal is expected.
- Begin rooftop demolition.
-
Utility investigation work on Mason Street and the south Broadway tributary.
|
Activities in October 2026 |
-
Hazardous materials abatement is expected to finish in the closed tunnel bore and building interior.
- Sidewalk and roadway demolition and shoring installation will begin inside the closed tunnel bore.
- Structural demolition and window removal will continue inside the building.
- Precast façade panels will be removed from the east and west sides of the building.
-
Structural steel work for the building façade will begin.
|
- 高峰時段或有交通延誤。駕駛人士如欲避免延誤,請改用附近及區域繞行路線。
|
- 已封閉的隧道及大樓內部將繼續進行有害物質清除及相關工程。
- 9月3日:Mason街將設置施工後勤區。沿 Mason Street 人行道將加設圍欄,並設置臨時行人通道。
- 9月4日至5日:進行 PG&E 煤氣切斷工程及路面修復。百老匯 (Broadway) 北側實施臨時停車限制。
- 9月8日起: 百老匯 (Broadway) 北、南側支路將開始設置施工區,以配合天台及外牆拆卸工程。大樓外圍將搭建棚架並加設收縮膜。原有停車位將改作行車線,並預計實施臨時停車限制。
-
9月11日至14日: 預計拆除龍形藝術裝置。
- 開始進行天台拆卸工程。
- 將在 Mason 街及百老匯 (Broadway) 南側分支路段進行公用設施勘查工程。
|
- 已封閉的隧道及大樓內部的有害物質清除工程預計將會完工。
-
施工人員將在已封閉的隧道內將展開人行道及路面拆卸工程,並進行臨時支撐工程。
- 大樓內部的結構拆卸及窗戶拆除工程將繼續進行。
- 將拆除大樓東、西兩面的預製外牆板 (Precast facade panels)。
- 大樓外牆的鋼結構工程亦將會展開。
|
|
|
|
Public Art Proposals | Shared by the San Francisco Arts Commission
公共藝術提案 | 資料由三藩市藝術委員會提供
|
|
|
|
Artist 藝術家: Jenifer K Wofford
Location 位置: Clubhouse 社區活動室
|
|
| Artist 藝術家: Cathy Lu
Location 位置: Walter U. Lum Pl. and Washington St.
|
|
|
|
Upcoming construction activities and traffic impacts: |
Activities in September 2026 |
Crews will continue demolition, off-hauling and waterproofing removal inside Portsmouth Square. Work will also advance on lower-level grade beams, including layout, dowel installation, formwork setup, rebar placement and the installation of embeds and anchor bolts.
To support this work, the site fence along Walter U. Lum Place is expected to move out to the curb. The sidewalk may close during work hours and pedestrians will be redirected to an alternate route; a protected walkway will be provided after work hours. Crews also will work near the elevators and build a temporary ramp to maintain access, with one elevator remaining operational at all times.
|
Activities in October 2026 |
Sewer line maintenance and replacement work is expected to take place on Walter U. Lum Place. Crews will perform trenching in the roadway to access and replace the sewer line. A temporary road closure, traffic changes, construction noises and parking restrictions are expected near the work area. The west-side sidewalk will remain open and local businesses will remain accessible to pedestrians.
Work is expected to take up to four weeks once underway. Confirmed dates and work hours will be shared once finalized.
|
施工人員將繼續在花園角内進行拆卸,清理廢料及拆卸防水層工程。下層地樑工程亦會持續推進,包括進行放樣和植筋,以及安裝模板、鋼筋、預埋件及地腳螺栓。
為配合工程,沿林華耀街 (Walter U. Lum Place) 的工地圍欄預計將移至路緣。施工時段內,相關人行道或需暫時封閉,非施工時段則會提供受保護的臨時行人通道。此外,工程人員將於電梯附近施工,並會搭建臨時斜道以維持通行,期間確保至少有一部電梯維持正常運作。
|
污水管道維修及更換工程預計在林華耀街 (Walter U. Lum Place) 進行。 施工人員將在路面開挖溝槽,以進入地下並更換污水管道。工程範圍附近將實施臨時封路及交通繞行,並或有施工噪音及停車限制。西側人行道將維持開放,沿線商戶照常營業。
工程展開後,預計需時四星期完成。確實施工日期及工作時間將於落實後公布。
|
Second Friday of each month at 10:00 a.m. at Walter U. Lum Place and Washington Street.
For language services or accessibility requests, please contact Noah Levy, project manager, at noah.levy@sfgov.org at least 48 hours before the meeting. Late requests will be honored if possible.
|
每月第二個星期五上午 10 時,在林華耀街 (Walter U. Lum Place) 與華盛頓 (Washington) 街交界處。
如需其他語言或無障礙支援,請於會議前至少 48 小時電郵項目經理Noah Levy: noah.levy@sfgov.org。逾時將盡力安排。
|
|
|
|
Public Art Proposals | Shared by the San Francisco Arts Commission
公共藝術提案 | 資料由三藩市藝術委員會提供
|
Artist 藝術家: Christine Wong Yap 葉黃嘉雯
Location 位置: Historic Reading Room 主閲讀室
|
|
|
|
The Chinatown Branch Library Renovation Project is expected to begin construction between November and December 2026. Additional updates will be shared as the project moves into the construction phase.
|
華埠麥禮謙圖書分館改善工程預計於 2026 年11至12月期間動工。隨著項目進入施工階段,市府將陸續提供更多最新動態。
|
|
|
|
Chinatown Transportation Updates
華埠交通最新消息 |
The City will monitor transportation conditions during construction activities. Traffic and transit reroutes are subject to change. Check SFMTA.com/gochinatown for the latest information before traveling. If the link does not open, please copy and paste it into your browser.
市府將於施工期間密切留意交通狀況。道路交通及公共運輸繞行安排或會因應實際情況作出調整。出發前,請瀏覽 SFMTA.com/gochinatown 獲取最新資訊。如未能打開,請將網址複製並貼到瀏覽器開啟。
|
|
| |
Chinatown Public Restroom Map
華埠公廁指南
|
|
|
|
| 1. Willie “Woo Woo” Wong Playground 黃顯護遊樂場
830 Sacramento Street, San Francisco, CA 94108
Spring/Summer: 8 a.m. - 8 p.m. | 春季及夏季:上午八時至晚上八時
Fall/Winter: 8 a.m. - 5:30 p.m. | 秋季及冬季:上午八時至下午五時半
|
2. Chinatown - Rose Pak Station Upper Plaza (Opening Sept. 19) |
華埠白蘭地鐵站上層廣場 (9月19日起開放)
943 Stockton Street, San Francisco, CA 94108
Monday - Saturday, 8 a.m. - 8 p.m. | 星期一至六:上午八時至晚上八時
|
3. St. Mary's Square | 聖瑪麗公園
651 California Street, San Francisco, CA 94108
Spring/Summer: 8 a.m. - 8 p.m. | 春季及夏季:上午八時至晚上八時
Fall/Winter: 8 a.m. - 5:30 p.m. | 秋季及冬季:上午八時至下午五時半
|
4. Betty Ann Ong Recreation Center | 鄧月薇華人康樂中心
1199 Mason Street, San Francisco, CA 94108
Tuesday - Friday: 10 a.m. - 9 p.m. | 星期二至五:上午十時至晚上九時
Saturday: 9 a.m. - 5 p.m. | 星期六:上午九時至下午五時
|
|
|
|
SHOP & DINE LOCAL IN CHINATOWN!
施工期間 請支持華埠本地商家 |
San Francisco Public Works is committed to supporting our neighborhood merchants during construction. Please continue to shop, dine and support local Chinatown small businesses while project improvements are underway!
Plan your visit with the Perfect Day in Chinatown guide: https://www.sf.gov/perfect-day-chinatown
Explore more local businesses through Office of Economic & Workforce Development's Shop and Dine SF page: https://www.sf.gov/shop-dine-sf
|
|
|
|
Get project updates and community information
獲取項目最新消息及社區資訊
|
|
| |
|
For project updates, please contact San Francisco Public Works Public Affairs at chinatownprojects@sfdpw.org or (415) 269-9199.
To receive construction updates in Chinese, please join our WeChat group to receive the latest project information. To join, please scan the WeChat QR code or contact us for assistance.
|
|
|
|
Manage your preferences | Opt Out using TrueRemove™
Got this as a forward? Sign up to receive our future emails.
View this email online.
|
49 South Van Ness Avenue | San Francisco, CA 94103 US
|
|
|
|
This email was sent to .
To continue receiving our emails, add us to your address book.
|
|
|
|
|