Next Crane Lift: Thursday, June 11
The biggest construction impact for most folks — outside of the wait for THE elevator — are the occasional crane picks. With roof contractors on site, materials are being lifted on a regular basis.
A lift of materials occurred Monday, June 8, and more are scheduled in the days ahead: Thursday, June 11, and Wednesday, June 17. During these picks the southwest corner of the fourth and third floors will need to be inaccessible from 5 a.m. to around 11 a.m., as a precaution.
On the fourth floor, this will primarily impact the Dean of Student Life’s office. On the third floor, the Vanport room, Campus AV storage and Smith 333 will be closed.
In an update from last week’s pick, the WRC | QRC has been OK’d to remain open during this work.
No entrances to Smith will be blocked but portions of the breezeway between Smith and FMH will be cordoned off. Pedestrian and bike traffic will be allowed to pass back and forth.
The semis with materials will be crossing the Park Blocks from SW 10th Ave.
Also FYI: A crane pick related to HVAC and elevator work is planned for Friday, June 19, 2026. While happening on the Juneteenth holiday, it will impact the use of the SW Broadway entrance. More information on hours and offices that may need to be left empty during that work is coming soon.