Chinatown Improvement Projects
Construction Updates
華埠改善工程最新消息 |
|
|
|
-
The Broadway Tunnel is now expected to fully close for ONE day on Sunday, Aug. 16, before the project begins an approximately 14-month partial closure with one lane open in each direction.
|
-
The Public Works Commission has approved the construction contract for the Chinatown library project, with construction expected to begin in fall 2026.
|
- 百老匯隧道(Broadway Tunnel)現預計只會於8月16日(星期日)全線封閉一天。隨後,該項目將進入為期約 14 個月的局部封閉階段,雙向將各保留一條行車線通行。
|
- 工務委員會已批准華埠圖書館項目的工程合約,工程預計於2026年秋季展開。
|
|
|
|
Upcoming construction activities and traffic impacts: |
Bridge demolition work is expected to take place from Aug. 1 to 15. From Aug. 1 to 10, crews will remove the pedestrian bridge over Kearny Street and the Hilton Hotel connection. From Aug. 10 to 15, crews will complete bridge removal on the park side of Kearny Street.
|
- July 30 to 31: Early demolition prep with partial closures on Kearny Street. Sidewalks remain open.
|
-
Aug. 1, 1:00 a.m. to Aug. 3, 5:00 a.m.: Bridge removal over Kearny Street (ZONE 2). Kearny Street (between Clay and Washington) and Portsmouth Square Garage closed. Local business access will remain available.
|
-
Aug. 3 to 7: Removal of the bridge section connected to the Hilton Hotel (ZONE 1), with partial lane and sidewalk closures near the work area.
|
-
Aug. 8, 1:00 a.m. to Aug. 10, 5:00 a.m.: Column removal on the west side of Kearny Street. Kearny Street (between Clay and Washington) and Portsmouth Square Garage closed. Local business access will remain available.
|
-
Aug. 10 to 15: Partial lane closure on Kearny Street and west-side sidewalk closure as crews complete demolition inside Portsmouth Square Park (ZONE 3).
|
行人天橋將於8月1-15日拆卸。8月1-10日期間,施工人員將先拆除橫跨乾尼街 Kearny St.及希爾頓酒店 Hilton Hotel 的天橋連接段;8月10-15日完成乾尼街公園一側的天橋拆卸。
|
-
7月30日至31日: 進行前期拆卸準備工作,乾尼街部分行車線封閉,人行道維持開放。
|
- 8 月1日凌晨1時至8月3日清晨5時: 拆除乾尼街上方的行人天橋(ZONE 2 區域)。乾尼街介乎企李街與華盛頓街的路段及花園角停車場將會關閉,沿線商戶仍可出入。
|
- 8月3日至7日: 拆除連接希爾頓酒店的天橋部分(ZONE 1 區域),施工範圍附近將實施部分行車線及人行道封閉。
|
- 8月8日凌晨1時至8月10日清晨5時: 拆除乾尼街西側的支柱。乾尼街介乎企李街與華盛頓街的路段及花園角停車場將會關閉,沿線商戶仍可出入。
|
- 8月10日至15日: 乾尼街部分行車線及西側人行道將會封閉,施工人員將在花園角內完成餘下拆卸工程(ZONE 3 區域)。
|
For the duration of this work, expect construction vehicles, lane closures, slower traffic, temporary “No Parking | Tow Away” zones and pedestrian detours along this section of Kearny Street. Please follow directions from on-site flaggers and posted signs, and allow extra travel time due to possible construction delays. Call 311 for questions about parking tickets or towed vehicles.
|
施工期間,乾尼街 Kearny Street 將有工程車輛出入,或需臨時封線、交通減慢、行人繞行及實施「禁止泊車/違例拖車」管制。請遵從現場指示並預留出行時間。停車罰單/拖車查詢:致電311。
|
Join the project team on the second Friday of each month at 10:00 a.m. at the corner of Walter U. Lum Place and Washington Street. Get construction updates, ask questions, and share feedback.
Interpretation services will be available in Chinese at all office hours. For other language services or accessibility requests, please contact Noah Levy, project manager, at noah.levy@sfgov.org at least 48 hours before the meeting. Late requests will be honored if possible.
|
項目團隊將於每月第二個星期五上午 10 時,在林華耀街 (Walter U. Lum Place) 與華盛頓 (Washington) 街交界處與市民會面。歡迎到場了解最新工程進展、提出查詢及分享意見。
現場提供中文翻譯。如需其他語言或無障礙支援,請於會議前至少 48 小時電郵項目經理Noah Levy: noah.levy@sfgov.org。逾時將盡力安排。
|
|
|
|
Upcoming construction activities and traffic impacts: |
FULL CLOSURE | AUG. 16, 7 a.m. – AUG. 17, 5 a.m.
| -
During the full closure, crews will restripe roadways, install traffic control devices and install protective decking above Broadway on the east side of the tunnel during construction.
|
PARTIAL CLOSURE | STARTING AUG. 17
|
-
Following the full closure, the south-side bore (eastbound) will close for approximately 7 months, with the north-side bore (westbound) carrying one lane of traffic in each direction.
- The north-side bore will then close for approximately 7 months, with the south bore carrying one lane in each direction.
-
During the partial closure, crews will begin hazardous materials abatement and related tunnel work inside the eastbound bore. Interior hazardous materials abatement also will continue inside the building.
- Expect traffic delays during peak travel times. Drivers who want to avoid delays can use the local and regional detour routes established for the full closure.
|
隧道全面封閉 | 8月16日上午7時至8月17日清晨5時
|
- 全面封閉期間,施工人員將重新劃設道路標線、安裝交通管制設施,並於隧道東側入口搭建施工防護平台。
|
- 全面封閉過後,南側隧道 (東行方向) 將封閉約7個月,期間北側隧道 (西行方向) 改為雙向單線行車。
-
其後,北側隧道將封閉約7個月,並改由南側隧道維持雙向各一條行車線。
- 局部封閉期間,施工人員將在東行隧道內展開有害物質清除及相關隧道工程。大樓內部的有害物質清除作業也將同步進行。
- 高峰時段或有交通延誤。駕駛人士如欲避免延誤,請改用附近及區域繞行路線。
|
|
|
|
Local Traffic Detours
附近車輛(交通)繞行
|
|
|
|
During Full Closure
隧道全面封閉期間
|
|
| During Partial Closure
隧道局部封閉期間
|
|
|
|
Regional Alternate Routes
區域繞行路線
|
|
|
|
The Public Works Commission approved the construction contract for the library project at its July 23 hearing. The contractor, S.J. Amoroso Construction CO. LLC, was selected through the City’s competitive bidding process based on best value for the work.
Construction is expected to begin in fall 2026. Additional updates will be shared as the project moves into the construction phase.
|
工務委員會已於 7 月 23 日的聽證會上批准華埠圖書館項目的施工合約。承建商S.J. Amoroso Construction CO. LLC是經市府的公開招標程序選出,並以「最佳整體價值」作為評選標準。
工程預計於 2026 年秋季開工。隨著項目進入施工階段,市府將陸續提供更多最新動態。
|
|
|
|
Chinatown Transportation Updates
華埠交通最新消息 |
The City will monitor transportation conditions during construction activities. Traffic and transit reroutes are subject to change. Check SFMTA.com/gochinatown for the latest information before traveling. If the link does not open, please copy and paste it into your browser.
市府將於施工期間密切留意交通狀況。道路交通及公共運輸繞行安排或會因應實際情況作出調整。出發前,請瀏覽 SFMTA.com/gochinatown 獲取最新資訊。如未能打開,請將網址複製並貼到瀏覽器開啟。
|
|
|
|
Get project updates and community information
獲取項目最新消息及社區資訊 |
|
|
|
|
For project updates, please contact San Francisco Public Works Public Affairs at chinatownprojects@sfdpw.org or (415) 269-9199.
To receive construction updates in Chinese, please join our WeChat group to receive the latest project information. To join, please scan the WeChat QR code or contact us for assistance.
|
|
|
|
Manage your preferences | Opt Out using TrueRemove™
Got this as a forward? Sign up to receive our future emails.
View this email online.
|
49 South Van Ness Avenue | San Francisco, CA 94103 US
|
|
|
|
This email was sent to julian.pham@sfdpw.org.
To continue receiving our emails, add us to your address book.
|
|
|
|
|